Las Vegas Convention Center Expansion Cost Balloons To $980.3M

October 9, 2019

Stay in the know with exclusive industry news, click here and subscribe to our eNewsletter today!

The cost of the Las Vegas Convention Center expansion project will increase $45.2 million to $980.3 million following a contract amendment approved Tuesday by the Las Vegas Convention and Visitors Authority’s board of directors.

Board members unanimously approved an increase from the guaranteed maximum price to assure the project will be completed in time for the 2021 CES.

The amended contract assures a temporary certificate of occupancy Dec, 14, 2020, substantial completion Jan. 1, 2021, final completion and a certificate of occupancy Feb. 14, 2021, and a final closeout July 27, 2021.

The new contract also approves additional upgraded features for the building that will house a 600,000-square-foot exhibition hall, meeting rooms and a rooftop patio for outdoor events.

Board members also approved contracts for professional oversight of the Boring Co.’s $48.7 million underground people-mover project.

In separate actions, the board unanimously approved a $525,500 contract with Kansas City, Missouri-based HNTB Corp. for third-party review services on the first-of-its-kind transportation system, and a contract for up to $2 million to Nova Geotechnical and Inspection Services LLC to provide material testing and special inspection services on the project.